Field work continues at FJORD building site

"We continue to work on the pile field of the building. The planned pace of work is at least eight to ten borehole injection piles per shift,” commented Oleksiy Borysov, FJORD project manager.

According to him, the list of already performed works includes: arrangement of the pit, arrangement of experimental piles of piles of the pile field with their subsequent testing by static loading. The piles of the retaining wall were arranged around the perimeter of the pit. And work has begun on the implementation of the pile field.