Progress of construction of FJORD cascades for december 2020

Active construction works are underway at FJORD.

Work on the development of the pit continues.

Work on the arrangement of the pile field (cascades 2, 3, 8, 9, parking lot) continues.

Works on the device of concrete preparation and base plates (cascades 5, 7) are completed.

Work has begun on reinforcement, concreting of vertical and horizontal elements - 3 floors (cascades 5, 7).

Works on reinforcement, concreting of vertical and horizontal elements - 3 floors (cascades 4, 6) are completed.

Reinforcement and concreting of vertical and horizontal elements of the 2nd floor are being carried out (cascades 4, 6).

Works on reinforcement, concreting of vertical and horizontal elements of the 3rd floor (cascade 7) are carried out.