Progress of construction of FJORD cascades for october 2020

Active construction works are underway at FJORD.

Work on the development of the pit continues.

Works on the arrangement of the pile field have been completed (cascades 6,7).

Work on the installation of test pile bushes (cascades 2,3,8) has been completed.

Works on the device of a pile field (cascades 2,3,8,9) are carried out.

Works on the device of concrete preparation under the base (cascades 5,7) are carried out.

Work has begun on reinforcement, concreting of vertical and horizontal elements of the 3rd floor (cascades 4.6).