Work plans for the summer period 2020

Oleksiy Borisov, the head of the FJORD project, answered the main questions: «what is the readiness of the project now?», «what are the plans for the summer and what should the builders have time to do?».

Oleksiy: «We carry out a complex of works of a zero cycle, we finish a fence of a pit on May, we continue earthworks.

On June-August - the arrangement of the pile field 1 and 2 launch complexes.

July-September - installation of the foundation slab for 1 and 2 launch complexes "